Residents of the Volta and Oti regions continue to grapple with persistent low voltage and frequent power outages, months after government announced plans to upgrade the ageing 69kV transmission network to a 161kV system to improve electricity supply.
The situation has heightened concerns among households and businesses, with residents questioning the pace of work on the project and demanding clarity on the allocation of funds, implementation timelines and measures being taken to address the immediate power challenges.
In April 2026, the Acting Managing Director of the Electricity Company of Ghana (ECG), Ing. Kwame Kpekpena, and a representative of the Ghana Grid Company Limited (GRIDCo), Ing. Frank A. Otchere, announced that government had made funds available for the first phase of a major electricity infrastructure upgrade covering the Volta Region and parts of the Oti Region.
The announcement was made during a meeting with the Volta Regional Minister, Hon. James Gunu, at his office in Ho, following concerns raised by the minister over persistent low voltage and frequent power outages in the region.
The engagement was intended to provide explanations for the electricity challenges and outline measures towards achieving a lasting solution.
Ing. Kpekpena disclosed that the project would involve upgrading the existing transmission line from Asiekpe to Ho from 69kV to 161kV, constructing a new transmission line of approximately 45 kilometres and establishing a new Bulk Supply Point (BSP) in Ho.
He explained that moving Ho from the existing 69kV network onto the 161kV system would significantly improve voltage stability and enhance the reliability of electricity supply to the Volta Region and adjoining communities in the Oti Region.
According to him, the current challenges are largely attributable to an ageing transmission network constructed in the 1980s, which has struggled to accommodate increasing electricity demand.
While several parts of the country operate on a 161kV transmission system, the Volta Region remains heavily dependent on the 69kV network, contributing to voltage fluctuations and frequent system tripping, particularly during peak evening periods.
Ing. Kpekpena said ECG and GRIDCo had introduced temporary interventions to ease pressure on the existing network but acknowledged the need for a more comprehensive infrastructure upgrade to address the problem permanently.
Speaking on behalf of GRIDCo, Ing. Frank A. Otchere reaffirmed the company’s commitment to the project, noting that the existing transmission infrastructure had served the region since the 1980s and required expansion and reinforcement to meet growing demand.
He disclosed that technical teams had assessed the Asiekpe-Ho transmission route, with design works underway and support from the Ministry of Energy and Green Transition.
Although projects of this nature would ordinarily require more than two years to complete, he said efforts were being made to restructure the implementation schedule to deliver the project within 12 months.
The Minister for Energy and Green Transition, Dr John Abdulai Jinapor, subsequently reaffirmed government’s commitment to improving electricity supply in the region during the launch of a turnkey electrification project to extend power to 206 communities across the 18 districts of the Volta Region in September 2026.
Dr Jinapor said government had committed substantial resources to strengthening electricity transmission infrastructure in Ho and other parts of the region.
He disclosed that work was underway on the 161kV transmission line from Asiekpe to Ho, which is expected to improve voltage levels and enhance the reliability of electricity supply.
The Minister also announced the construction of a new power substation to provide the regional capital with a dedicated power transformer and transmission lines.
The facility, he explained, would ease pressure on the existing transformer and transmission infrastructure while improving electricity supply to Ho and surrounding communities.
Despite the assurances and project announcements, residents continue to express frustration over what they describe as worsening electricity supply conditions.
Some residents fear that the persistent low voltage and outages could affect businesses, household activities and productivity, particularly during the Christmas season when electricity demand is expected to increase.
They have therefore called on ECG, GRIDCo and the Ministry of Energy and Green Transition to accelerate the implementation of the upgrade and introduce more effective interim measures to stabilise electricity supply while the major infrastructure works progress.